DEP, EPA propose alternatives for next phase of CSO tank construction, by Oscar Fock

In early August, the New York City Department of Environmental Protection announced they had finished the first phase of the construction of the combined sewer overflow (CSO) tank that will sit between the Gowanus Canal and Nevins Street. This phase, which included building a deep underground concrete perimeter around the site, has been a source of concern for neighbors for months, as noxious odors have evaporated from the excavated soil. In our last issue, we wrote about an email thread between Gowanus residents, agency representatives and elected officials, detailing how questions have gone unanswered, promises have fallen through and frustration has grown.

Because of the criticism of the handling of the first phase, which did not receive any community input prior to work starting, the DEP and the Environmental Protection Agency (EPA) attended the most recent Gowanus Community Advisory Group (CAG) meeting to share with the community the options for phase two.

After setting the concrete walls, DEP, the agency in charge of construction (under EPA oversight), plans to excavate the lot to make room for the tank. The city agency claims less contaminated soil will be excavated this time as the digging wont go as deep as during the first phase. Still, several community members have expressed concern over how phase two will impact the neighborhood. Some have, therefore, asked for a tent to be erected over the site to keep odors from escaping into the neighborhood. A tent covering the entire site is not a viable option, however, according to EPA Remedial Project Manager Thomas Mongelli. It would add 25 months to the current timeline of 10 months for phase two and incur an additional $90 million in costs, based on DEP estimates. The equipment needed to ventilate the tent and clean the air would not physically fit within the footprint of the site,” said Mongelli.

Similarly, a moveable tent would delay the project almost 2.5 years and cost $91 million more than the DEPs current plan, which does not include a tent. Covering the southern half — the half with the most contaminated soil — is not as expensive as the other two and would only add 19 months to the current timeline. All three options, Mongelli noted, would reduce odors but likely not eliminate them. Finally, the fourth option to the base plan would be to accelerate the schedule without a tent. This option has the greatest risk of odor impacts but would make the second phase four months shorter than initially estimated. It would mean that about 1,500 tons of dirt would have to be shipped off via truck every day, which is realistic, said Kevin Clarke, portfolio manager at the DEP.

John Prince, deputy director at EPA Region 2, clarified following Mongellis presentation that the estimates of additional time and costs are not to be taken as fact. Dont take the timeframes as gospel, and dont take the costs as gospel. Theyre the best the city can do to approximate what the cost additions would be to implement these options,” he said.

Prince added that getting the work done so that sewage is kept out of the canal is also important.

The alternatives are still being evaluated and no decision has been made, said Mongelli, indicating that the community, while it has now had the chance to see the different potential routes, will have no say in what plan is chosen. This was not met with a lot of enthusiasm from community members. The notion that somehow decisions will be made on one of these four options without consulting the community is, quite honestly, shocking. Shocking,” said Dr. Hildegaard Link.

The EPAs plan is to hold another meeting where the different options are presented to the community in more detail, but the federal agencys representatives at the CAG meeting did not say when that would be.

Share:

Facebook
Twitter
LinkedIn

Comments are closed.

On Key

Related Posts

Gilbert Gonzalez honored at Rec Center Christmas event, by Nathan Weiser

The Red Hook Rec Center was in the spirit of giving last month, hosting their annual holiday bash with food, music and presents for children. It was organized by Isiah Forde of the Center and Andre Richey of New Leader Hoops. The first holiday party hosted by the Rec Center in 2015. There was pizza from Mark’s on Van Brunt

Cautious optimism on the Gowanus smell front, by Oscar Fock

In December, The New York City Department of Environmental Protection (DEP), overseen by the Environmental Protection Agency (EPA), began the second phase of construction of Gowanus’s two Combined Sewer Overflow (CSO) tanks after pausing work since August. Because of the design of the much of New York’s sewer system, where stormwater and sewage water both go through the same pipe,

A great day at PS 676, by Nathan Weiser

Red Hook’s Harbor Middle School held their holiday spectacular showcase the last day before winter break. It began in the auditorium with performances and videos from the school year so far. After that was finished, there were beverages, snacks, holiday crafts and photos. The YMCA after-school program showed their holiday video titled “Mischief at 676, the Red Hook story.” Next